Example takeoff from a public bid set: a 7-sheet office renovation. 555 new devices by group, lighting by type, plus existing, relocated and demolition.

Electrician on a ladder installing a light fixture in the ceiling grid of an office under renovation
  • Power

    169

  • Lighting

    139

  • Switches & controls

    98

  • Data, fire alarm, access

    148

  • Panels & equipment

    1

  • Total new

    555

Example takeoff from a public bid set. This is a seven-sheet renovation of one office floor. It has power, data, fire alarm, access control and lighting. It is a larger and messier set than the park restroom. We counted 555 new devices. The drawings come from an open public bid. We leave out the project, owner, city and engineers on purpose.

What this sample shows

  • A set with new, existing, relocated and demolished work.
  • Tables by group, and the lighting sheet by fixture type.
  • A rule that trips up counters: group notation such as S3 (a,b,c).
  • Real open questions: a missing panel schedule, an unclear fire alarm symbol, furniture-fed receptacles and an occupancy sensor quantity.

For how to read the columns, see the sample takeoffs hub.

The set

Sheet Content
E001 Symbols, notes, sheet list
E002 Existing power riser diagram (not counted)
E003 Panel schedules and details
E004 Luminaire schedule and details
E111 Power and special systems plan (counted)
E121 Lighting plan (counted)
ED111 Demolition plans (summarized only)

Result by group

These are our own numbers from a run in November 2026 with Claude Sonnet and our takeoff instructions. This is not an independent test: an earlier run on this same set missed grouped switches, and we then added a rule to our instructions (see below). The numbers are new work only.

Group New devices
Power 169
Lighting 139
Switches & controls 98
Data, fire alarm, access 148
Panels & equipment 1
Total new 555

Outside the new total, the run counted 10 relocated exit signs and 6 existing items (a USB receptacle, two linear fixtures and three existing panels).

Full line table

Power: 169 new

Item Qty Status Confidence
Duplex receptacle 20A, wall (standard, circuits 2B-n, new box) 97 new high
Duplex receptacle, "NEW DEVICE, EXISTING OUTLET" (new device in existing box) 4 new medium
Duplex receptacle with USB ports (USB), new box 39 new high
Duplex USB receptacle, "NEW DEVICE, EXISTING OUTLET" 1 new medium
Duplex USB receptacle marked "EXIST." (existing to remain) 1 existing medium
GFCI duplex receptacle (GF) 4 new high
Special receptacle 6-30R (popcorn popper), circuit 2B-36,38 1 new high
Receptacle in furniture (tag F, 2B-27 and 2B-15) 4 new medium
Junction box J for undercarpet wireway 120V connection (keynote 3) 6 new high
Junction box J for HVAC controls at new VAV box (2B-23) 1 new medium
Junction box J above ceiling for future video displays (with data stub) 4 new medium
Junction box J_P furniture power connection (label FP) 2 new medium
Surface floor power outlet, 4 x 5-20R, UCW end (power only) 3 new high
Surface floor power+data outlet, 4 x 5-20R + 4 keystone, UCW end 3 new high

Lighting: 139 new

Item Qty Status Confidence
Type A1 LED 2x2 troffer 3300 lm, 26.3 W - normal circuit 19 new high
Type A1 LED 2x2 troffer - emergency circuit 2EHA-5 (shaded) 6 new high
Type A2 LED 2x2 troffer 6000 lm, 49 W - normal circuit 81 new high
Type A2 LED 2x2 troffer - emergency circuit 2EHA-5 (shaded) 7 new high
Type A3 LED 2x2 troffer 7200 lm, 58.6 W 8 new high
Type C1 LED 6 in recessed downlight 24.7 W - normal circuit 13 new high
Type C1 downlight - emergency circuit 2EHA-5 1 new high
Type UC LED undercabinet strip 2 W/ft (runs, length not measured) 4 new medium
Exit sign EXC ceiling-mounted (relocated existing unit per schedule) 10 relocated medium
Linear fixtures labelled EXISTING TO REMAIN (no tag) 2 existing medium

Switches & controls: 98 new

Item Qty Status Confidence
Dimmer switch S_D (single location, incl. 3 lettered dimmers cS_D bS_D aS_D stack) 31 new high
Dimmer switch S_D marked 3-WAY 4 new medium
Three-way switch S3 (single) 4 new medium
Three-way switch S3 (a,b,c) gang notation - 2 groups x 3 6 new medium
Four-way switch S4 (a,b,c) gang notation - 1 group x 3 3 new low
Wall-box vacancy sensor switch (V) 6 new medium
Ceiling occupancy sensor symbol OS (keynote 5: contractor determines quantity) 37 new low
Automatic generator transfer device AGTD (keynote 7) 7 new medium

Data, fire alarm, access: 148 new

Item Qty Status Confidence
Data/telecom outlet (triangle), wall 63 new medium
Telecom outlet with blank cover feeding UCW (keynote 4) 3 new high
Data stub (triangle) at J above ceiling for future video 4 new medium
Data outlet in furniture (F triangle) 2 new medium
J_T furniture telecom pathway box (label FT) 2 new medium
AVT 2-gang power/data TV outlet 4 new high
Wireless access point AP (owner IT furnishes; EC provides 1-1/4 in conduit) 13 new high
Card reader provision CR (box on wall) 7 new high
J box 4x4 above ceiling for card reader/lock power (keynote 6, 2B-34) 7 new high
Door holder j-box DH (connect to fire alarm) 2 new high
FA ceiling horn/strobe 75cd (F in circle, H) 24 new medium
FA wall strobe 75cd (square F with circle) 1 new medium
FA manual pull station (square F) 1 new medium
FA ceiling smoke detector (S hexagon) 13 new high
FA ceiling rate-of-rise/heat detector (H hexagon) 2 new high

Panels & equipment: 1 new

Item Qty Status Confidence
New 30A 2-pole breaker (N) in panel 2B, ckt 36/38 popcorn popper 1 new high
Panel 2B existing (branch circuit panel) 1 existing high
Panel 2A existing 1 existing high
Panel 2HA existing (lighting 480/277) 1 existing high

Lighting sheet by fixture type

On sheet E121, tags matched the luminaire schedule. Some fixtures sit on the emergency circuit and are shaded on the plan, so we split them out and then merged them by type.

Type Count Note
A1 (2x2 troffer) 25 19 normal, 6 emergency
A2 (2x2 troffer) 88 81 normal, 7 emergency
A3 (2x2 troffer) 8
C1 (6 in downlight) 14 13 normal, 1 emergency
UC (undercabinet strip) 4 runs, length not measured
EXC (exit sign) 10 relocated, not new

New, existing, relocated, demolished

Notes and leaders change the status of a device. Examples: "existing to remain", "new device, existing outlet", salvaged and reinstalled. We keep each status as its own line, so the new total holds only new work.

The demolition sheet was not counted item by item. The run gave a rough size with low confidence: about 150 lighting fixtures, about 15 exit or emergency units, and on the power side roughly 100 to 130 receptacles. This is a scale, not a count, and none of it is in the 555.

A rule that matters: S3 (a,b,c)

On the lighting sheet, switches carry notes such as S3 (a,b,c) and S4 (a,b,c). One symbol means one device per listed letter, so three devices.

In an earlier blind run, a different, larger Claude model (Fable 5, no instructions) counted each grouped symbol as one switch. It reported 6 three-way and 1 four-way switch, and 549 new devices in all. The reference count was 10 and 3. That left it 6 switches short on the sheet (4 three-way and 2 four-way).

We added a rule for group notation to our instructions after that miss. The run above counted 10 three-way and 3 four-way switches. Be careful with that comparison: the rule came from this very set, and our instructions were tuned after an earlier run on it, so the result shows the fix works here, not that the method is right on every set. The run flagged the four-way group as low confidence, and raised a question to confirm three devices per group.

Reference comparison

A commercial takeoff service counted the same set (all statuses together). We read its totals from its free preview.

Commercial service Fable 5 blind (earlier run) Sonnet with instructions
E111 power and special systems 319 319 318
E121 lighting 248 240 249

On E121, all luminaire types, occupancy sensors, AGTD devices and exit signs matched by type. Dimmers were 35 in our run and 34 at the service. On E111 we could not compare item by item, because the service shows only the total for free.

The Sonnet figure of 249 on E121 is the 139 new lighting devices, 10 relocated exit signs and 2 existing linear fixtures, plus the 98 switches and controls (139 + 10 + 2 + 98). The Fable 5 figure of 240 is 8 below the service. The six missed grouped switches explain six of those 8; we did not trace the other two, and we did not recheck the Fable 5 run sheet by sheet, so read that column as a rough guide.

There is no hand-verified reference for this set. Matching another tool is not proof of accuracy.

Open questions found

  1. Missing emergency panel schedule. The emergency lighting circuit (24 devices) has no panel schedule in the set.
  2. Unclear fire alarm symbol. One symbol with a subscript H is used 24 times on ceilings. Is it a horn and strobe, or a speaker and strobe? The legend does not say. Who supplies and programs the devices?
  3. Furniture-fed receptacles. Four receptacles, two data outlets and four furniture connection boxes are tagged as part of the furniture. The furniture vendor may supply them.
  4. Occupancy sensor quantity. There are 37 sensor symbols, but a note says the contractor determines the quantity. The real number of sensors can be higher, and demolition notes allow reuse of existing ones.

The run also asked about circuits whose plan count did not match the panel row (loads of 0.9 kVA against 1.3 kVA on one circuit), security doors with no hardware drawn, and several "new device, existing outlet" notes.

Panel cross-check

Most circuits matched the panel schedule within about 0.2 kVA. The run flagged three power circuits and one lighting circuit as mismatched and turned each into a question.

Limits

  • This is not an independent test. Our instructions were tuned after an earlier run on this set.
  • The count has no hand-verified reference. It was compared to a commercial service and to another model run.
  • Many receptacle, data and fire alarm lines are medium confidence for the reasons above.
  • Demolition quantities are rough.
Free to try on a sample

Upload your drawings

Send a PDF drawing set. The takeoff counts every electrical device by sheet, lists the open questions it found in the drawings, and emails you when it is ready. Export the result as CSV or JSON.

Early access: 1 free project up to 5 plan sheets. Paid plans start at $19.90 a month; cancel anytime.

  • Upload a PDF drawing set
  • Devices counted by sheet
  • Open questions listed for you
  • Export to CSV or JSON