Sample takeoff: park restroom, 3 sheets, 82 devices

Example takeoff from a public bid set: a park restroom with 3 sheets. 82 devices on sheet E1.01, main device types checked by hand, a panel-load check and RFIs.

Small masonry park restroom building with an attached picnic canopy and exterior wall pack lights
  • Power

    28

  • Lighting

    31

  • Switches & controls

    8

  • Data, fire alarm, access

    3

  • Panels & equipment

    12

  • Total

    82

Example takeoff from a public bid set. This is a small, clean set: a park restroom building with a picnic canopy. It has three electrical sheets. We counted the devices on the plan sheet, E1.01, and checked the count by hand. The drawings come from an open public bid. We leave out the project, the owner and the engineers on purpose.

What this sample shows

  • A full takeoff of one small sheet, line by line, with groups and confidence.
  • A check of the count against the panel schedule.
  • The open questions (RFIs) that the sheets raise.

To learn how to read the columns, see the sample takeoffs hub.

The set

Sheet Content
E1.01 Power plan and lighting plan (the counting sheet)
E2.01 One-line diagram and panel schedule
E3.01 Symbol legend and specifications

The sheets are a vector PDF. Text can be extracted from it, so tags such as C, P, W, ST, EG, X2, OS, EF, J and GFCI can be counted next to the picture.

Result: 82 devices

In a blind test in November 2026 we ran an AI agent (Claude Fable 5, a larger model than the Sonnet the product uses; see the hub) on the PDF. It saw only the drawings. A commercial takeoff service had counted the same set and reported 82 devices. We also counted the main device types by hand (not every group), and the numbers agreed (one receptacle near the panel was hard to read, 7 or 8). The agent's group totals matched the service: Power 28, Lighting 31, Switches and controls 8, Data and fire alarm 3, Panels and equipment 12.

The product itself (Claude Sonnet with our takeoff instructions) was then run on the same PDF five times, on November 14 and 15, 2026. Each run reported 82 devices. This is not an independent test: the instructions were written while this set was already known to us.

The agent listed two more lines, which it flagged itself as items that other contractors may supply. They are shown below and not added to the 82.

Group Devices
Power 28
Lighting 31
Switches & controls 8
Data, fire alarm, access 3
Panels & equipment 12
Total 82

Full line table

All items below are new work. The status column is left out because every line is new. Group totals follow the table headings.

Power: 28

Item Qty Confidence
Duplex receptacle, exterior, WR/WP/GFCI with in-use cover 4 high
Duplex receptacle, 20A (general) 3 high
Duplex receptacle, GFCI, above-counter symbol 3 high
Duplex receptacle, dedicated circuit (refrigerator) 3 high
Duplex receptacle, dedicated circuit (future refrigerator) 2 medium
Fourplex (quad) receptacle at telephone board 1 high
Junction box, ceiling (CLG.) for ceiling fan 5 high
Junction box, weatherproof, building signage 1 high
Junction box, wall (no circuit or note shown) 6 medium

Lighting: 31

Item Qty Confidence
Type C - 6in recessed LED downlight 12 high
Type P - LED vandal-resistant canopy fixture 4 high
Type W - LED full cut-off wall pack 8 high
Type ST - LED suspended linear 3 high
Type EG - mullion-mounted emergency light 2 high
Type X2 - LED exit sign / emergency combo 2 high

Switches & controls: 8

Item Qty Confidence
Occupancy sensor switch ($OS), restroom dual-tech (keyed note 3) 6 high
Occupancy sensor switch ($OS), storage IR (keyed note 2) 2 high

Data, fire alarm, access: 3

Item Qty Confidence
Telephone mounting board (T.M.B.) 4'x8' with #6 Cu ground 1 high
Junction box, 120V for fire alarm control panel 1 high
Junction box, 120V for tamper & flow (FA bell) 1 high
Fire alarm control panel (FACP symbol) (listed, not in the 82; may be supplied by others) 1 medium

Panels & equipment: 12

Item Qty Confidence
Panelboard 'A', 200A 208Y/120V 3ph 4W MLO, flush 1 high
Service entrance section (SES) 200A NEMA 3R 1 high
Intersystem bonding terminal (listed, not in the 82; may be supplied by others) 1 medium
Disconnect switch 2 high
Equipment connection - water heater WH-A (208V 2P, A-35,37) 1 high
Equipment connection - outdoor unit OU-A1 (208V 2P, A-39,41) 1 high
Equipment connection - exhaust fan EF-A1..A6 (120V, A-1) 6 high

Panel-load cross-check

The panel schedule lists a load for each circuit. A count that matches those loads is more trustworthy. Circuit 1 serves the restroom downlights and the exhaust fans:

  • 12 downlights at 12 VA each = 144 VA
  • 6 exhaust fans at 100 VA each = 600 VA
  • Total = 744 VA

The panel schedule shows 744 VA for circuit 1. Circuit 3 also matched (703 VA from the exterior and canopy fixtures), as did the receptacle circuits. See how to read electrical blueprints for the method.

Open questions found

The agent raised these questions. We rewrote them in plain words.

  1. Six wall junction boxes, one per restroom, have no circuit and no note. What do they serve? Hand dryers are a guess.
  2. The notes require time clocks, but none is drawn. How many, and where?
  3. A note requires a disconnect for each motor. None is drawn at the six exhaust fans.
  4. A general note makes receptacles within 6 ft of a sink GFCI. Three receptacles scale inside that distance but are drawn as plain duplex.
  5. A fire alarm panel symbol is drawn. Does another contractor supply the panel and the system?
  6. A lighting note says emergency lighting comes from an emergency power system, but the one-line diagram shows none.
  7. Who supplies and installs the five ceiling fans at the picnic area?
  8. A note refers to sheet "E2.0", but the sheet is E2.01.

What this sample does not show

  • The sheets E2.01 and E3.01 were used as sources, not counted. A commercial service also raised questions about available fault current against breaker ratings and the wiring method. Our test did not cover those.
  • Another run, of Claude Sonnet without our instructions, got the line items right but made a sum error, did not extract the text, and did not run the panel check. That is why the product adds a fixed method and computes totals in code.
  • This is a small, clean set. See the office renovation and the music stage renovation for larger or harder sets.
Free to try on a sample

Upload your drawings

Send a PDF drawing set. The takeoff counts every electrical device by sheet, lists the open questions it found in the drawings, and emails you when it is ready. Export the result as CSV or JSON.

Early access: 1 free project up to 5 plan sheets. Paid plans start at $19.90 a month; cancel anytime.

  • Upload a PDF drawing set
  • Devices counted by sheet
  • Open questions listed for you
  • Export to CSV or JSON